NASCLAMech/Plumbmedium5% of exam part

On the mechanical plan, find equipment tag EF-11; then read the equipment schedule. What notes is shown?

Correct Answer

D) Drain pan

Sheet M-809 shows EF-11 on the plan excerpt; the matching schedule row lists Drain pan in the Notes column.

Answer Options
A
Backdraft damper
B
VFD ready
C
Curb mounted
D
Drain pan

Why This Is the Correct Answer

Sheet M-809 shows EF-11 on the plan excerpt; the matching schedule row lists Drain pan in the Notes column.

Why the Other Options Are Wrong

Option A: Backdraft damper

Backdraft damper is the notes entry for RTU-10, not for the mark located on the plan.

Option B: VFD ready

VFD ready is the notes entry for WH-12, not for the mark located on the plan.

Option C: Curb mounted

Curb mounted is the notes entry for PMP-13, not for the mark located on the plan.

Memory Technique

Plan-to-table hook for mechanical and equipment 10: tag EF-11 selects the row; Notes supplies the field.

Reference Hint

Open Sheet M-809; locate EF-11 in the plan excerpt before reading the schedule row.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.