Roof trusses have been set, but the required temporary restraint and diagonal bracing are incomplete. A roofing supplier wants to land bundles on the trusses. What should happen?

Correct Answer

C) Complete required restraint and bracing and verify loading limits before placing bundles

Trusses are unstable until properly restrained and braced, and construction loads must follow the truss and BCSI guidance. Other choices load an unstable system or remove needed bracing.

Answer Options
A
Land bundles near midspan to balance the trusses, leaving truss bracing unverified
B
Base the truss bracing response on load only every other truss
C
Complete required restraint and bracing and verify loading limits before placing bundles
D
The framing crew should remove lateral restraint so bundles can sit flat

Why This Is the Correct Answer

Trusses are unstable until properly restrained and braced, and construction loads must follow the truss and BCSI guidance. Other choices load an unstable system or remove needed bracing.

Why the Other Options Are Wrong

Option A: Land bundles near midspan to balance the trusses, leaving truss bracing unverified

Choice A (Land bundles near midspan to balance the trusses) is rejected because the choice would not get the project to Complete required restraint and bracing and verify loading limits before placing bundles, which is the Truss bracing result verified by the source.

Option B: Base the truss bracing response on load only every other truss

In wood framing, Load only every other truss is the wrong selection for Truss bracing: it leaves the work at an informal or incomplete stage, while Truss bracing requires Complete required restraint and bracing and verify loading limits before placing bundles.

Option D: The framing crew should remove lateral restraint so bundles can sit flat

Choice D gives Remove lateral restraint so bundles can sit flat. Its specific error: it answers the Truss bracing prompt with the wrong practical move.

Memory Technique

Tag the scene with truss bracing: wrong actor or wrong timing means the fix is not Complete required restraint and bracing and verify loading limits before placing bundles.

Reference Hint

Open BCSI: Guide to Good Practice for Handling, Installing, Restraining & Bracing of Metal Plate Connected Wood Trusses, 2018/2025; use the index entry or section for "BCSI temporary restraint, bracing, and construction loading guidance" to confirm that Trusses are unstable until properly restrained and braced, and construction loads must follow the truss and BCSI guidance.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.