Roof trusses have been set, but the required temporary restraint and diagonal bracing are incomplete. A roofing supplier wants to land bundles on the trusses. What should happen?
Correct Answer
C) Complete required restraint and bracing and verify loading limits before placing bundles
Trusses are unstable until properly restrained and braced, and construction loads must follow the truss and BCSI guidance. Other choices load an unstable system or remove needed bracing.
Why This Is the Correct Answer
Trusses are unstable until properly restrained and braced, and construction loads must follow the truss and BCSI guidance. Other choices load an unstable system or remove needed bracing.
Why the Other Options Are Wrong
Option A: Land bundles near midspan to balance the trusses, leaving truss bracing unverified
Choice A (Land bundles near midspan to balance the trusses) is rejected because the choice would not get the project to Complete required restraint and bracing and verify loading limits before placing bundles, which is the Truss bracing result verified by the source.
Option B: Base the truss bracing response on load only every other truss
In wood framing, Load only every other truss is the wrong selection for Truss bracing: it leaves the work at an informal or incomplete stage, while Truss bracing requires Complete required restraint and bracing and verify loading limits before placing bundles.
Option D: The framing crew should remove lateral restraint so bundles can sit flat
Choice D gives Remove lateral restraint so bundles can sit flat. Its specific error: it answers the Truss bracing prompt with the wrong practical move.
Memory Technique
Tag the scene with truss bracing: wrong actor or wrong timing means the fix is not Complete required restraint and bracing and verify loading limits before placing bundles.
Reference Hint
Open BCSI: Guide to Good Practice for Handling, Installing, Restraining & Bracing of Metal Plate Connected Wood Trusses, 2018/2025; use the index entry or section for "BCSI temporary restraint, bracing, and construction loading guidance" to confirm that Trusses are unstable until properly restrained and braced, and construction loads must follow the truss and BCSI guidance.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A single-wythe modular brick screen wall has 300 sf of net face area. Using 6.75 modular brick per square foot and adding 5 percent for cuts and breakage, what brick quantity is closest?
Next Question
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?