Roof trusses have been set, but the required temporary restraint and diagonal bracing are incomplete. A roofing supplier wants to land bundles on the trusses. What should happen?
Correct Answer
C) Complete required restraint and bracing and verify loading limits before placing bundles
Trusses are unstable until properly restrained and braced, and construction loads must follow the truss and BCSI guidance. Other choices load an unstable system or remove needed bracing.
Why This Is the Correct Answer
Trusses are unstable until properly restrained and braced, and construction loads must follow the truss and BCSI guidance. Other choices load an unstable system or remove needed bracing.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A single-wythe modular brick screen wall has 300 sf of net face area. Using 6.75 modular brick per square foot and adding 5 percent for cuts and breakage, what brick quantity is closest?
Next Question
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?