A single-wythe modular brick screen wall has 300 sf of net face area. Using 6.75 modular brick per square foot and adding 5 percent for cuts and breakage, what brick quantity is closest?
Correct Answer
D) 2,126 brick
Base quantity is 300 x 6.75 = 2,025 brick. Add 5 percent: 2,025 x 1.05 = 2,126.25, so 2,126 brick is closest. Other choices: 1,950 is too low, 2,025 omits the allowance, and 2,250 uses an excessive allowance.
Why This Is the Correct Answer
Base quantity is 300 x 6.75 = 2,025 brick. Add 5 percent: 2,025 x 1.05 = 2,126.25, so 2,126 brick is closest.
Why the Other Options Are Wrong
Option A: 1,950 brick
brick quantity, choice a: 1,950 brick backs into 39,000 when divided by 5 percent; the accepted setup gives 42,520 on that same base.
Option B: 2,025 brick
brick quantity, choice b: 2,025 brick stops after base quantity is 300 x 6.75 = 2025 brick and omits the final step to 2,126 brick.
Option C: 2,250 brick
brick quantity, choice d: 2,250 brick backs into 45,000 when divided by 5 percent; the accepted setup gives 42,520 on that same base.
Memory Technique
Say the brick quantity rule aloud as a chain; the chain ends at 2,126 brick, not an intermediate stop.
Reference Hint
Open Modern Masonry - Brick, Block, Stone, 9th Ed., 2020; use the index entry or section for "Modular brick quantity estimating" to confirm that Base quantity is 300 x 6.75 = 2,025 brick.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass