Before backfill begins, what does pipe bedding primarily provide?
Correct Answer
A) Uniform support and protection from point loads
Uniform support and protection from point loads is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 67.
Why This Is the Correct Answer
Uniform support and protection from point loads is the controlling requirement
Why the Other Options Are Wrong
Option B: Base the bedding response on paint protection
Choice B gives Only paint protection. Its specific error: it leaves the work at an informal or incomplete stage, while Bedding requires.
Option C: Classify the condition as a way to reverse slope
Choice C (A way to reverse slope) is rejected because it leaves out the controlling Bedding result.
Option D: Classify the condition as a substitute for testing
In site construction, A substitute for testing is the wrong selection for Bedding: it treats Bedding as optional.
Memory Technique
Link bedding to its book condition; a different condition means a different answer than Uniform support and protection from point loads.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use the index entry or section for "Pipe bedding" to confirm that Uniform support and protection from point loads is the controlling requirement
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
On the door plan, locate door D83; then use the door schedule. What rating is listed?
Next Question
A single-wythe modular brick screen wall has 300 sf of net face area. Using 6.75 modular brick per square foot and adding 5 percent for cuts and breakage, what brick quantity is closest?