A rooftop unit motor has a running amp value on the equipment submittal and a much higher starting demand. What should the GC coordinate before rough-in?
Correct Answer
C) Confirm motor starters, disconnects, conductors, and protection are coordinated with the approved equipment data
Motors affect both mechanical equipment placement and electrical distribution. Before rough-in, the GC should coordinate starters, disconnects, conductors, and protection with the approved equipment data, including starting characteristics. Ignoring starting demand or waiting until set day risks rework.
Why This Is the Correct Answer
Motors affect both mechanical equipment placement and electrical distribution. Before rough-in, the GC should coordinate starters, disconnects, conductors, and protection with the approved equipment data, including starting characteristics. Ignoring starting demand or waiting until set day risks rework.
Why the Other Options Are Wrong
Option A: Ignore motor starting because it affects only the mechanical contractor
Motor starting affects the electrical system even though the equipment is mechanical, so it cannot be left outside electrical coordination.
Option B: The coordinator should use the nameplate running amps as the only electrical coordination item
Running amps alone omit starter, disconnect, conductor, protection, and starting-demand coordination shown in the approved submittal data.
Option D: Delay electrical coordination until the unit is set on the roof
Waiting until the unit is on the roof means raceways, disconnect locations, and feeder work may already be wrong.
Memory Technique
Tag the scene with motor equipment coordination: wrong actor or wrong timing means the fix is not Confirm motor starters, disconnects, conductors, and protection are coordinated with the approved equipment data.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use by topic index - motors / equipment coordination to confirm that Motors affect both mechanical equipment placement and electrical distribution.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
An EIFS wall terminates above finished earth at the base of a building. What minimum clearance is commonly required by ANSI/EIMA installation practice at grade?
Next Question
A directed change uses rented drying equipment for 4 days at $650 per day. The contract allows 15 percent markup on equipment cost. What equipment amount should be proposed?
