A rooftop unit motor has a running amp value on the equipment submittal and a much higher starting demand. What should the GC coordinate before rough-in?
Correct Answer
C) Confirm motor starters, disconnects, conductors, and protection are coordinated with the approved equipment data
Motors affect both mechanical equipment placement and electrical distribution. Before rough-in, the GC should coordinate starters, disconnects, conductors, and protection with the approved equipment data, including starting characteristics. Ignoring starting demand or waiting until set day risks rework.
Why This Is the Correct Answer
Motors affect both mechanical equipment placement and electrical distribution. Before rough-in, the GC should coordinate starters, disconnects, conductors, and protection with the approved equipment data, including starting characteristics. Ignoring starting demand or waiting until set day risks rework.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
An EIFS wall terminates above finished earth at the base of a building. What minimum clearance is commonly required by ANSI/EIMA installation practice at grade?
Next Question
A directed change uses rented drying equipment for 4 days at $650 per day. The contract allows 15 percent markup on equipment cost. What equipment amount should be proposed?