In a guaranteed maximum price contract, what is contractor contingency typically used for?
Correct Answer
D) Covered costs within the agreed GMP risk allocation, not owner-added scope.
GMP contingency is governed by the contract and is not a blank check for owner changes.
Why This Is the Correct Answer
GMP contingency is governed by the contract and is not a blank check for owner changes.
Why the Other Options Are Wrong
Option A: Base the gMP contingency response on unlimited owner scope growth
Choice A gives Unlimited owner scope growth. Its specific error: it answers the GMP contingency prompt with the wrong practical move.
Option B: Select bid bond replacement for gMP contingency although the file does not verify gMP contingency
Choice B (Bid bond replacement.) is rejected because it treats GMP contingency as optional.
Option C: All design errors regardless of contract
In procurement and contracting, All design errors regardless of contract. is the wrong selection for GMP contingency: the choice would not get the project to Covered costs within the agreed GMP risk allocation, not owner-added scope.
Memory Technique
Use GMP contingency as the label and Covered costs within the agreed GMP risk allocation, not owner-added scope. as the definition to recall under pressure.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Guaranteed maximum price" to confirm that GMP contingency is governed by the contract and is not a blank check for owner changes.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
