Which delta tag identifies the clouded area on the procurement sheet?
Correct Answer
C) Delta 4 Roof
The answer is printed in the addendum cloud excerpt as Delta 4 Roof; the other listed entries belong to different rows or boundaries.
Why This Is the Correct Answer
The answer is printed in the addendum cloud excerpt as Delta 4 Roof; the other listed entries belong to different rows or boundaries.
Why the Other Options Are Wrong
Option A: Delta 1 Lobby
Delta 1 Lobby appears elsewhere on the same addendum cloud excerpt, but it is not the marked condition being asked.
Option B: Delta 2 Storage
Delta 2 Storage appears elsewhere on the same addendum cloud excerpt, but it is not the marked condition being asked.
Option D: Delta 3 Loading
Delta 3 Loading appears elsewhere on the same addendum cloud excerpt, but it is not the marked condition being asked.
Memory Technique
addendum cloud cue on G-827: cloud boundary selects the delta tag.
Reference Hint
Open Sheet G-827; read the addendum cloud excerpt and choose the entry attached to the marked condition.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Silt fence is needed on three sides of a 220 ft by 140 ft disturbed pad; the remaining 220 ft side is protected by a stabilized construction entrance. Adding 5 percent for overlaps and returns, what fence length should be ordered?
Next Question
In a guaranteed maximum price contract, what is contractor contingency typically used for?