A sealant subcontractor prices 1,260 lf of control joints. The bid includes 8 percent extra for mockups, corners, and waste. What linear footage should be carried?
Correct Answer
D) 1,361 lf
Adjusted footage is 1,260 x 1.08 = 1,360.8 lf, rounded to 1,361 lf. Other choices omit waste, use about 4 percent, or add too much material.
Why This Is the Correct Answer
Adjusted footage is 1,260 x 1.08 = 1,360.8 lf, rounded to 1,361 lf. Other choices omit waste, use about 4 percent, or add too much material.
Why the Other Options Are Wrong
Option A: 1,260 lf
sealant joint material, choice a: 1,260 lf is produced by 1,260. The error is using that partial/alternate setup.
Option B: 1,310 lf
sealant joint material, choice b: 1,310 lf backs into 1,212.96 when divided by 1.08; the accepted setup gives 1,260.19 on that same base.
Option C: 1,512 lf
sealant joint material, choice d: 1,512 lf backs into 1,400 when divided by 1.08; the accepted setup gives 1,260.19 on that same base.
Memory Technique
Say the sealant joint material rule aloud as a chain; the chain ends at 1,361 lf, not an intermediate stop.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Sealant joint quantity allowance" to confirm that Adjusted footage is 1,260 x 1.08 = 1,360.8 lf, rounded to 1,361 lf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass