Open RFIs are 4, 8, 11, and 13 days old. What is their average age?
Correct Answer
B) 9 days
Average RFI age is (4 + 8 + 11 + 13) / 4 = 9 days.
Why This Is the Correct Answer
Average RFI age is (4 + 8 + 11 + 13) / 4 = 9 days.
Why the Other Options Are Wrong
Option A: 8 days
rfi average age, choice a: 8 days uses the wrong numerator, denominator, or percent conversion.
Option C: 10 days
rfi average age, choice c: 10 days is wrong because 10 days uses the wrong numerator, denominator, or percent conversion.
Option D: 36 days
rfi average age, choice d: 36 days uses the wrong numerator, denominator, or percent conversion.
Memory Technique
Keep a checkpoint beside RFI average age: if one number is skipped, the option drifts away from 9 days.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Average RFI age is (4 + 8 + 11 + 13) / 4 = 9 days.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Site backfill is scheduled before the service grounding electrode work has been inspected. What should the superintendent coordinate?
Next Question
A sealant subcontractor prices 1,260 lf of control joints. The bid includes 8 percent extra for mockups, corners, and waste. What linear footage should be carried?
