EstatePass
NASCLAElectricalmedium3% of exam part

Site backfill is scheduled before the service grounding electrode work has been inspected. What should the superintendent coordinate?

Correct Answer

C) Verify the grounding electrode/bonding work is installed and inspected before it is concealed

Grounding electrode and bonding work can be concealed by site work, slabs, or finishes, so the superintendent must coordinate installation and inspection before cover-up. Memory notes, post-energization installation, or equipment delivery do not replace inspection of the grounding path.

Answer Options
A
Backfill first and document the location from memory
B
The superintendent should install grounding components only after permanent power is energized
C
Verify the grounding electrode/bonding work is installed and inspected before it is concealed
D
The superintendent should omit the grounding review if the transformer has arrived

Why This Is the Correct Answer

Grounding electrode and bonding work can be concealed by site work, slabs, or finishes, so the superintendent must coordinate installation and inspection before cover-up. Memory notes, post-energization installation, or equipment delivery do not replace inspection of the grounding path.

Why the Other Options Are Wrong

Option A: Backfill first and document the location from memory

A memory note cannot verify buried grounding work after it is covered and leaves the project with no inspectable installation record.

Option B: The superintendent should install grounding components only after permanent power is energized

Grounding and bonding must be coordinated as part of the service installation; waiting until permanent power is energized is too late.

Option D: The superintendent should omit the grounding review if the transformer has arrived

Transformer delivery is a logistics milestone, not proof that the grounding electrode and bonding work are complete and inspected.

Memory Technique

Use the phrase "problem, control, result" for grounding electrode coordination; the result side is Verify the grounding electrode/bonding work is installed and inspected before it is concealed.

Reference Hint

Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use by topic index - grounding and bonding / concealed work coordination to confirm that Grounding electrode and bonding work can be concealed by site work, slabs, or finishes, so the superintendent must coordinate installation and inspection before cover-up.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.