What does OSHA require when employees work in excavations where water is accumulating?
Correct Answer
C) Protection from hazards caused by water accumulation using appropriate controls.
Employees may not work in excavations with accumulated water unless protected by adequate precautions.
Why This Is the Correct Answer
Employees may not work in excavations with accumulated water unless protected by adequate precautions.
Why the Other Options Are Wrong
Option A: Treat the condition as requiring no controls if production is urgent
In site construction, No controls if production is urgent is the wrong selection for Excavation water accumulation: the choice would not get the project to Protection from hazards caused by water accumulation using appropriate controls.
Option B: Base the excavation water accumulation response on a daily report note only
The trap in B is Only a daily report note. That selection is wrong because the option delays or omits the controlling step.
Option D: Limit excavation water accumulation to a deeper trench only
Choice D (Only a deeper trench) is rejected because it tries to bypass the Excavation water accumulation checkpoint.
Memory Technique
File excavation water accumulation under a cover note: condition first, number or duty second, answer Protection from hazards caused by water accumulation using appropriate controls.
Reference Hint
Open OSHA 29 CFR 1926 Subpart P; EPA Construction General Permit concepts where applicable; use OSHA 1926.651(h) to confirm that Employees may not work in excavations with accumulated water unless protected by adequate precautions.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass