A porcelain tile floor measures 1,125 sf after cabinet deductions. The installer orders 12 percent extra for cuts and breakage. What order area is required?
Correct Answer
D) 1,260 sf
Order area is 1,125 x 1.12 = 1,260 sf. Other choices use a smaller allowance, add too much, or apply waste before deductions.
Why This Is the Correct Answer
Order area is 1,125 x 1.12 = 1,260 sf. Other choices use a smaller allowance, add too much, or apply waste before deductions.
Why the Other Options Are Wrong
Option A: 1,180 sf
tile flooring, choice a: 1,180 sf counts a different spacing, panel, or repeated member quantity.
Option B: 1,310 sf
tile flooring, choice c: 1,310 sf counts a different spacing, panel, or repeated member quantity.
Option C: 1,350 sf
tile flooring, choice d: 1,350 sf counts a different spacing, panel, or repeated member quantity.
Memory Technique
Say the tile flooring rule aloud as a chain; the chain ends at 1,260 sf, not an intermediate stop.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Tile flooring quantity allowance" to confirm that Order area is 1,125 x 1.12 = 1,260 sf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?