A pump fails a functional performance test during commissioning. What should happen next?
Correct Answer
C) Log the issue, assign responsibility, correct the cause, and retest.
Commissioning deficiencies are tracked through correction and verification.
Why This Is the Correct Answer
Commissioning deficiencies are tracked through correction and verification.
Why the Other Options Are Wrong
Option A: The project manager should hide the result from the owner
In general project requirements, Hide the result from the owner. is the wrong selection for Commissioning deficiency: it leaves the work at an informal or incomplete stage, while Commissioning deficiency requires Log the issue, assign responsibility, correct the cause, and retest.
Option B: Make release final retainage immediately the answer for commissioning deficiency
The trap in B is Release final retainage immediately. That selection is wrong because it names a financial document or payment mechanism, not the Commissioning deficiency action/result stated by Log the issue, assign responsibility, correct the cause, and retest.; Commissioning failures are logged, corrected, and retested.
Option D: Convert the failed test into a warranty certificate
Choice D (Convert the failed test into a warranty certificate.) is rejected because it points to Convert the failed test into a warranty certificate. but.
Memory Technique
Use the phrase "problem, control, result" for commissioning deficiency; the result side is Log the issue, assign responsibility, correct the cause, and retest.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - quality control / nonconformance / corrective action to confirm that Commissioning deficiencies are tracked through correction and verification.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A porcelain tile floor measures 1,125 sf after cabinet deductions. The installer orders 12 percent extra for cuts and breakage. What order area is required?
Next Question
A feeder termination has no torque record, and the installer used an adjustable wrench by feel. What should be required before acceptance?