NASCLAGeneral Reqmedium22% of exam part

A pump fails a functional performance test during commissioning. What should happen next?

Correct Answer

C) Log the issue, assign responsibility, correct the cause, and retest.

Commissioning deficiencies are tracked through correction and verification.

Answer Options
A
The project manager should hide the result from the owner
B
Make release final retainage immediately the answer for commissioning deficiency
C
Log the issue, assign responsibility, correct the cause, and retest.
D
Convert the failed test into a warranty certificate

Why This Is the Correct Answer

Commissioning deficiencies are tracked through correction and verification.

Why the Other Options Are Wrong

Option A: The project manager should hide the result from the owner

In general project requirements, Hide the result from the owner. is the wrong selection for Commissioning deficiency: it leaves the work at an informal or incomplete stage, while Commissioning deficiency requires Log the issue, assign responsibility, correct the cause, and retest.

Option B: Make release final retainage immediately the answer for commissioning deficiency

The trap in B is Release final retainage immediately. That selection is wrong because it names a financial document or payment mechanism, not the Commissioning deficiency action/result stated by Log the issue, assign responsibility, correct the cause, and retest.; Commissioning failures are logged, corrected, and retested.

Option D: Convert the failed test into a warranty certificate

Choice D (Convert the failed test into a warranty certificate.) is rejected because it points to Convert the failed test into a warranty certificate. but.

Memory Technique

Use the phrase "problem, control, result" for commissioning deficiency; the result side is Log the issue, assign responsibility, correct the cause, and retest.

Reference Hint

Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - quality control / nonconformance / corrective action to confirm that Commissioning deficiencies are tracked through correction and verification.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.