A feeder termination has no torque record, and the installer used an adjustable wrench by feel. What should be required before acceptance?
Correct Answer
A) Verify the termination with a calibrated torque tool to the manufacturer's value
Electrical terminations need to be made to the manufacturer's specified torque using proper tools when torque is specified. Other choices rely on feel or conceal a connection that may be loose or overtightened.
Why This Is the Correct Answer
Electrical terminations need to be made to the manufacturer's specified torque using proper tools when torque is specified. Other choices rely on feel or conceal a connection that may be loose or overtightened.
Why the Other Options Are Wrong
Option B: The installer should accept the work if the conductor cannot be pulled out by hand
A hand pull only shows the conductor did not slip loose; it does not prove the lug was tightened to the manufacturer's torque value.
Option C: Loosen and retighten the lug without checking the listed value
Loosening and retightening without the listed value repeats the same uncontrolled workmanship problem.
Option D: Cover the termination with tape to prevent movement
Tape can conceal a termination but cannot correct an undertightened or overtightened lug.
Memory Technique
Tag the scene with terminal torque verification: wrong actor or wrong timing means the fix is not Verify the termination with a calibrated torque tool to the manufacturer's value.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use by topic index - conductors / overcurrent / box fill to confirm that Electrical terminations need to be made to the manufacturer's specified torque using proper tools when torque is specified.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
