A welder is ready to cut embeds beside stored packaging, but no hot-work controls or fire watch have been set up. What should be done?
Correct Answer
A) Set up the required hot-work controls before cutting begins
Hot work should not begin until the required permit, combustible control, extinguisher, and fire-watch measures are in place. Other choices leave ignition hazards unmanaged.
Why This Is the Correct Answer
Hot work should not begin until the required permit, combustible control, extinguisher, and fire-watch measures are in place. Other choices leave ignition hazards unmanaged.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The framing crew lead reads the detail note: approved work to date is $2,677,000; retainage is 10 percent and prior payments are $1,358,000. What current payment is due?
Next Question
A porcelain tile floor measures 1,125 sf after cabinet deductions. The installer orders 12 percent extra for cuts and breakage. What order area is required?
