A welder is ready to cut embeds beside stored packaging, but no hot-work controls or fire watch have been set up. What should be done?
Correct Answer
A) Set up the required hot-work controls before cutting begins
Hot work should not begin until the required permit, combustible control, extinguisher, and fire-watch measures are in place. Other choices leave ignition hazards unmanaged.
Why This Is the Correct Answer
Hot work should not begin until the required permit, combustible control, extinguisher, and fire-watch measures are in place. Other choices leave ignition hazards unmanaged.
Why the Other Options Are Wrong
Option B: Cut first because the work is brief, leaving hot work control unverified
The trap in B is Cut first because the work is brief. That selection is wrong because it points to Cut first because the work is brief, but.
Option C: The project manager should move only the largest box and start
Choice C gives Move only the largest box and start. Its specific error: the option delays or omits the controlling step.
Option D: Treat the item as a closeout correction tied to hot work control
Choice D (Rely on the building alarm system instead of a fire watch) is rejected because it leaves out the controlling Hot work control result: Set up the required hot-work controls before cutting begins.
Memory Technique
Use the phrase "problem, control, result" for hot work control; the result side is Set up the required hot-work controls before cutting begins.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Hot-work planning and fire prevention" to confirm that Hot work should not begin until the required permit, combustible control, extinguisher, and fire-watch measures are in place.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The framing crew lead reads the detail note: approved work to date is $2,677,000; retainage is 10 percent and prior payments are $1,358,000. What current payment is due?
Next Question
A porcelain tile floor measures 1,125 sf after cabinet deductions. The installer orders 12 percent extra for cuts and breakage. What order area is required?
