A fill area needs 960 compacted cubic yards. If shrinkage from loose to compacted volume is 15 percent, what loose volume is needed?
Correct Answer
C) 1,129 cy
Loose volume is 960 / 0.85 = 1,129 cy.
Why This Is the Correct Answer
Loose volume is 960 / 0.85 = 1,129 cy.
Why the Other Options Are Wrong
Option A: 1,016 cy
loose fill volume, choice a: 1,016 cy implies compacted volume is about 94.49 percent of loose volume; the accepted shrinkage factor is 85 percent in Loose volume is 960 / 0.85 = 1,129 cy.
Option B: 1,241 cy
loose fill volume, choice b: 1,241 cy implies compacted volume is about 77.36 percent of loose volume; the accepted shrinkage factor is 85 percent in Loose volume is 960 / 0.85 = 1,129 cy.
Option D: 960 cy
loose fill volume, choice d: 960 cy implies compacted volume is about 100 percent of loose volume; the accepted shrinkage factor is 85 percent in Loose volume is 960 / 0.85 = 1,129 cy.
Memory Technique
Keep a weep path beside loose fill volume: if one number is skipped, the option drifts away from 1,129 cy.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use by topic index - earthwork volume / swell / shrink to confirm that Loose volume is 960 / 0.85 = 1,129 cy.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study