A 45 kVA single-phase transformer is served at 240 V. Ignoring losses, what primary current is drawn at full load?

Correct Answer

A) 187.5 A

Single-phase current is VA divided by volts: 45,000 / 240 = 187.5 A. Other choices divide by 416 V, multiply by a power factor assumption, or divide by 120 V.

Answer Options
A
187.5 A
B
108.3 A
C
216.0 A
D
375.0 A

Why This Is the Correct Answer

Single-phase current is VA divided by volts: 45,000 / 240 = 187.5 A. Other choices divide by 416 V, multiply by a power factor assumption, or divide by 120 V.

Why the Other Options Are Wrong

Option B: 108.3 A

single-phase transformer current, choice a: 108.3 A backs into 0.58 when divided by 45000 / 240; the accepted setup gives 1 on that same base.

Option C: 216.0 A

single-phase transformer current, choice c: 216.0 A backs into 1.15 when divided by 45000 / 240; the accepted setup gives 1 on that same base.

Option D: 375.0 A

single-phase transformer current, choice d: 375.0 A backs into 2 when divided by 45000 / 240; the accepted setup gives 1 on that same base.

Memory Technique

Store single-phase transformer current with its last math move; nearby answers are usually unfinished versions of 187.5 A.

Reference Hint

Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use the index entry or section for "Single-phase power calculation" to confirm that Single-phase current is VA divided by volts: 45,000 / 240 = 187.5 A.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.