A tenant floor has 14 single-leaf office doors, 3 pair doors, and 2 single-leaf restroom doors. Counting one hardware set per active leaf, how many hardware sets are needed?
Correct Answer
C) 22 sets
Single-leaf doors require 14 + 2 = 16 sets. Three pair doors have two active leaves each, so 3 x 2 = 6 sets. Total hardware sets are 16 + 6 = 22. Other choices count each pair as one set or add extra restroom sets.
Why This Is the Correct Answer
Single-leaf doors require 14 + 2 = 16 sets. Three pair doors have two active leaves each, so 3 x 2 = 6 sets. Total hardware sets are 16 + 6 = 22. Other choices count each pair as one set or add extra restroom sets.
Why the Other Options Are Wrong
Option A: 19 sets
door hardware sets, choice a: 14 + 3 + 2 gives 19 sets. That calculation adds three listed values.
Option B: 20 sets
door hardware sets, choice b: 20 sets is off by 2 from the checked result 22 sets because it misuses the 2 item (2 single-leaf restroom doors).
Option D: 24 sets
door hardware sets, choice c: 24 sets is off by 2 from the checked result 22 sets because it misuses the 2 item (2 single-leaf restroom doors).
Memory Technique
Store door hardware sets with its last math move; nearby answers are usually unfinished versions of 22 sets.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Door hardware quantity takeoff" to confirm that Single-leaf doors require 14 + 2 = 16 sets.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass