A grading area has 2,850 cubic yards of cut and 3,120 cubic yards of fill required. What is the net import before shrink/swell?

Correct Answer

D) 270 cu yd import

Net is 3,120 fill - 2,850 cut = 270 cu yd import before shrink/swell.

Answer Options
A
270 cu yd export
B
5,970 cu yd import
C
135 cu yd export
D
270 cu yd import

Why This Is the Correct Answer

Net is 3,120 fill - 2,850 cut = 270 cu yd import before shrink/swell.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.