A grading area has 2,850 cubic yards of cut and 3,120 cubic yards of fill required. What is the net import before shrink/swell?
Correct Answer
D) 270 cu yd import
Net is 3,120 fill - 2,850 cut = 270 cu yd import before shrink/swell.
Why This Is the Correct Answer
Net is 3,120 fill - 2,850 cut = 270 cu yd import before shrink/swell.
Why the Other Options Are Wrong
Option A: 270 cu yd export
net cut fill, choice a: 270 cu yd export repeats the numeric result but changes the required label or rounding.
Option B: 5,970 cu yd import
net cut fill, choice c: 5,970 cu yd import equals 2,850 + 3,120. That adds those two listed numbers.
Option C: 135 cu yd export
net cut fill, choice d: 135 cu yd export backs into 0.5 when divided by 270; the accepted setup gives 1 on that same base.
Memory Technique
Keep a switch beside net cut fill: if one number is skipped, the option drifts away from 270 cu yd import.
Reference Hint
Open Pipe and Excavation Contracting, 2011; use by topic index - earthwork volume / swell / shrink to confirm that Net is 3,120 fill - 2,850 cut = 270 cu yd import before shrink/swell.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?