The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
Correct Answer
D) Price each alternate separately as requested by the bid form
Alternates are separate bid items that let the owner add or deduct defined scope while comparing bids. Other choices hide the comparison basis or omit requested bid information.
Why This Is the Correct Answer
Alternates are separate bid items that let the owner add or deduct defined scope while comparing bids. Other choices hide the comparison basis or omit requested bid information.
Why the Other Options Are Wrong
Option A: The contractor should blend all alternates into one hidden contingency
In procurement and contracting, Blend all alternates into one hidden contingency is the wrong selection for Alternates: it points to Blend all alternates into one hidden contingency, but.
Option B: The contractor should submit only the lowest alternate
The trap in B is Submit only the lowest alternate. That selection is wrong because the action skips the timing, documentation, or field-control step needed for Alternates.
Option C: The contractor should omit alternates until after the contract is signed
Choice C gives Omit alternates until after the contract is signed. Its specific error: it leaves out the controlling Alternates result: Price each alternate separately as requested by the bid form.
Memory Technique
Link alternates to its book condition; a different condition means a different answer than Price each alternate separately as requested by the bid form.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Alternates in bidding" to confirm that Alternates are separate bid items that let the owner add or deduct defined scope while comparing bids.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A grading area has 2,850 cubic yards of cut and 3,120 cubic yards of fill required. What is the net import before shrink/swell?
Next Question
The closeout specifications say the one-year correction period starts at substantial completion unless otherwise stated. Which date should be used for that correction period?
