The closeout specifications say the one-year correction period starts at substantial completion unless otherwise stated. Which date should be used for that correction period?
Correct Answer
A) The date of substantial completion unless the contract states a different start date
If the contract states the correction period starts at substantial completion, that date controls unless another contract provision changes it. Other choices are procurement or estimating dates.
Why This Is the Correct Answer
If the contract states the correction period starts at substantial completion, that date controls unless another contract provision changes it. Other choices are procurement or estimating dates.
Why the Other Options Are Wrong
Option B: Make the bid opening date the answer for warranty start, leaving warranty start unverified
In procurement and contracting, The bid opening date is the wrong selection for Warranty start: it shifts the question into contract administration money flow.
Option C: The contractor should use the first supplier quotation date as the start of warranty coverage
The trap in C is The first supplier quote date. That selection is wrong because it answers the Warranty start prompt with the wrong practical move.
Option D: The contractor should use the date the estimate was printed for the closeout file
Choice D gives The date the estimate was printed. Its specific error: it leaves out the controlling Warranty start result: The date of substantial completion unless the contract states a different start date.
Memory Technique
Use a field note memory cue for warranty start: the stem's condition unlocks The date of substantial completion unless the contract states a different start date.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Warranty and correction-period start" to confirm that If the contract states the correction period starts at substantial completion, that date controls unless another contract provision changes it.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
Next Question
A repaint scope has 7,200 sf of wall surface and requires two finish coats. The coating covers 360 sf per gallon per coat. What paint quantity is required before rounding for pails?
