An anchored veneer elevation is 36 ft long and 14 ft high. Using the prescriptive maximum of 2.67 sq ft per anchor, what minimum number of veneer anchors is required before adding opening-edge anchors?
Correct Answer
A) 189 anchors
Area is 36 x 14 = 504 sf. Divide by 2.67 sf per anchor: 504/2.67 = 188.76, so at least 189 anchors are needed. Other choices result from rounding down, using about 3 sf per anchor, or adding an arbitrary allowance not requested.
Why This Is the Correct Answer
Area is 36 x 14 = 504 sf. Divide by 2.67 sf per anchor: 504/2.67 = 188.76, so at least 189 anchors are needed. Other choices result from rounding down, using about 3 sf per anchor, or adding an arbitrary allowance not requested.
Why the Other Options Are Wrong
Option B: 172 anchors
veneer anchors, choice a: 172 anchors backs into 0.91 when divided by 189; the accepted setup gives 1 on that same base.
Option C: 176 anchors
veneer anchors, choice c: 176 anchors omits a required add-on/subtraction; the numeric gap is 13.
Option D: 200 anchors
veneer anchors, choice d: 200 anchors adds an extra unstated add-on/subtraction; the numeric gap is 11.
Memory Technique
Say the veneer anchors rule aloud as a chain; the chain ends at 189 anchors, not an intermediate stop.
Reference Hint
Open International Building Code 2021 or 2024; use IBC anchored masonry veneer area per anchor to confirm that Area is 36 x 14 = 504 sf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass