A 40 ft by 12 ft CMU wall is built with nominal 8 by 16 face units. Using 1.125 units per square foot and a 5 percent ordering allowance, what unit count should be ordered?
Correct Answer
C) 567 units
Wall area is 40 x 12 = 480 sf. At 1.125 CMU/sf, base quantity is 480 x 1.125 = 540 units. With a 5 percent ordering allowance, 540 x 1.05 = 567 units. Other choices: 540 omits the allowance, 594 uses a 10 percent allowance, and 432 uses one unit per square foot incorrectly.
Why This Is the Correct Answer
Wall area is 40 x 12 = 480 sf. At 1.125 CMU/sf, base quantity is 480 x 1.125 = 540 units. With a 5 percent ordering allowance, 540 x 1.05 = 567 units.
Why the Other Options Are Wrong
Option A: 540 units
cmu quantity, choice a: the answer choice lifts 540 units from the working line.
Option B: 594 units
cmu quantity, choice c: 594 units backs into 528 when divided by 1.125; the accepted setup gives 504 on that same base.
Option D: 432 units
cmu quantity, choice d: 432 units backs into 27 when divided by 16; the accepted setup gives 35.44 on that same base.
Memory Technique
Keep a fastener row beside CMU quantity: if one number is skipped, the option drifts away from 567 units.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Masonry quantity takeoff - CMU face units" to confirm that Wall area is 40 x 12 = 480 sf.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass