A new accessible entrance threshold is installed at 3/4 in. high with an abrupt vertical face. What is the correct field response?
Correct Answer
B) Correct the threshold to the new-construction height and bevel requirements
New accessible thresholds are limited to 1/2 in. maximum, with beveling above 1/4 in.; a 3/4 in. abrupt threshold is not acceptable for new construction. Other choices misuse an existing-threshold allowance or create a trip condition.
Why This Is the Correct Answer
New accessible thresholds are limited to 1/2 in. maximum, with beveling above 1/4 in.; a 3/4 in. abrupt threshold is not acceptable for new construction. Other choices misuse an existing-threshold allowance or create a trip condition.
Why the Other Options Are Wrong
Option A: Accept it because 3/4 in. is allowed for every new threshold
Choice A gives Accept it because 3/4 in. is allowed for every new threshold. Its specific error: Accept it because 3/4 in. is allowed for every new threshold is a different published number than the cited Threshold accessibility value; ICC A117.1-2017 Section 404.2.5 thresholds supports Correct the threshold to the new-construction height and bevel requirements.
Option C: Add a mat on one side, leaving the threshold and leave threshold accessibility unverified
In doors, windows, and glazing, Add a mat on one side and leave the threshold is the wrong selection for Threshold accessibility: the choice would not get the project to Correct the threshold to the new-construction height and bevel requirements, which is the Threshold accessibility result verified by the source.
Option D: Label the entrance as accessible only for staff and leave threshold accessibility unchecked
The trap in D is Label the entrance as accessible only for staff. That selection is wrong because it leaves the work at an informal or incomplete stage, while Threshold accessibility requires Correct the threshold to the new-construction height and bevel requirements; New accessible thresholds must meet the 1/2 in.
Memory Technique
Use the phrase "problem, control, result" for threshold accessibility; the result side is Correct the threshold to the new-construction height and bevel requirements.
Reference Hint
Open ICC A117.1-2017 Accessible and Usable Buildings and Facilities; use ICC A117.1-2017 Section 404.2.5 thresholds to confirm that New accessible thresholds are limited to 1/2 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
