On the finish plan, locate room R300; then use the finish schedule. What floor finish is listed?
Correct Answer
B) LVT-3
Sheet F-800 shows R300 on the plan excerpt; the matching schedule row lists LVT-3 in the Floor Finish column.
Why This Is the Correct Answer
Sheet F-800 shows R300 on the plan excerpt; the matching schedule row lists LVT-3 in the Floor Finish column.
Why the Other Options Are Wrong
Option A: SHEET VINYL
SHEET VINYL is the floor finish entry for R301, not for the mark located on the plan.
Option C: EPOXY-2
EPOXY-2 is the floor finish entry for R302, not for the mark located on the plan.
Option D: SEALED CONC
SEALED CONC is the floor finish entry for R303, not for the mark located on the plan.
Memory Technique
Plan-to-table hook for finish and 01: tag R300 selects the row; Floor Finish supplies the field.
Reference Hint
Open Sheet F-800; locate R300 in the plan excerpt before reading the schedule row.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
