A K-series open-web steel joist is seated on its support. Which minimum OSHA end attachment is acceptable for each end of that joist?
Correct Answer
D) Two 1/8 in. fillet welds 1 in. long, or two 1/2 in. bolts
OSHA 1926.757(b)(1) requires each end of a K-series steel joist to be attached with a minimum of two 1/8 in. fillet welds 1 in. long, or two 1/2 in. bolts, or equivalent. Other choices underattach the joist or use the larger LH/DLH detail.
Why This Is the Correct Answer
OSHA 1926.757(b)(1) requires each end of a K-series steel joist to be attached with a minimum of two 1/8 in. fillet welds 1 in. long, or two 1/2 in. bolts, or equivalent. Other choices underattach the joist or use the larger LH/DLH detail.
Why the Other Options Are Wrong
Option A: Base the k-series joist attachment response on one 1/2 in. bolt at one end only
Choice A (One 1/2 in. bolt at one end only) is rejected because One 1/2 in. bolt at one end only is a different published number than the cited K-series joist attachment value; 29 CFR 1926.757(b)(1) supports T.
Option B: Two 1/4 in. fillet welds 2 in. long
In metals work, Two 1/4 in. fillet welds 2 in. long is the wrong selection for K-series joist attachment: Two 1/4 in. fillet welds 2 in. long is a different published number than the cited K-series joist attachment value; 29 CFR 1926.757(b)(1) supports T.
Option C: Four 1/2 in. bolts plus a field weld
The trap in C is Four 1/2 in. bolts plus a field weld. That selection is wrong because Four 1/2 in. bolts plus a field weld is a different published number than the cited K-series joist attachment value; 29 CFR 1926.757(b)(1) supports T.
Memory Technique
Make k-series joist attachment a tabbed card: cite the exact condition, then choose Two 1/8 in. fillet welds 1 in. long, or two 1/2 in. bolts.
Reference Hint
Open Technical Digest No. 9 - Steel Joists & Joist Girders, 3rd Ed., 2008; 29 CFR 1926 Subpart R; use 29 CFR 1926.757(b)(1) to confirm that OSHA 1926.757(b)(1) requires each end of a K-series steel joist to be attached with a minimum of two 1/8 in.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass