EstatePass
NASCLAContractsmedium27% of exam part

A deck installer checks the fastening plan: who normally decides whether listed alternates are accepted when awarding the contract?

Correct Answer

A) The owner under the bid and contract documents

The owner under the bid and contract documents is the controlling requirement: the distractors are related-looking contract or field terms, but they do not match the cited requirement for review item 249.

Answer Options
A
The owner under the bid and contract documents
B
Base the alternate acceptance response on the low subcontractor
C
Select the building inspector for alternate acceptance
D
Limit alternate acceptance to the surety after final payment

Why This Is the Correct Answer

The owner under the bid and contract documents is the controlling requirement

Why the Other Options Are Wrong

Option B: Base the alternate acceptance response on the low subcontractor

In procurement and contracting, The low subcontractor only is the wrong selection for Alternate acceptance: the option delays or omits the controlling step.

Option C: Select the building inspector for alternate acceptance

The trap in C is The building inspector. That selection is wrong because the option does not produce the required Alternate acceptance outcome.

Option D: Limit alternate acceptance to the surety after final payment

Choice D gives The surety after final payment. Its specific error: it tries to bypass the Alternate acceptance checkpoint.

Memory Technique

Link alternate acceptance to its book condition; a different condition means a different answer than The owner under the bid and contract documents.

Reference Hint

Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Alternates and award" to confirm that The owner under the bid and contract documents is the controlling requirement

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.