Under bidding documents that reserve award selection to the owner, who decides which listed alternates to accept?
Correct Answer
A) The owner under the bid and contract documents
The owner makes the award selection under the bidding rules and applicable law, including acceptance of alternates. A subcontractor, inspector or surety does not ordinarily choose the owner’s purchased scope. The AIA A701 comparative reference illustrates that role; its specific selection procedure is not imposed on every procurement. Source: https://assets.aiacontracts.com/ctrzdweb02/zdpdfs/a701_2018.scose_.comparative.pdf
Why This Is the Correct Answer
The owner makes the award selection under the bidding rules and applicable law, including acceptance of alternates. A subcontractor, inspector or surety does not ordinarily choose the owner’s purchased scope. The AIA A701 comparative reference illustrates that role; its specific selection procedure is not imposed on every procurement. Source: https://assets.aiacontracts.com/ctrzdweb02/zdpdfs/a701_2018.scose_.comparative.pdf
Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →
More NASCLA Questions
A contract permits payment for stored materials only with specified documentation. Which submission supports that payment review?
A tempered glass panel is 5 ft by 9 ft. The supplier weight is 6.5 lb per square foot. What is the panel weight before hardware?
The owner will buy major equipment directly, while the contractor remains responsible for coordination and installation. What must be clarified before the purchase is released?
Which minimum eccentric gravity load and distance does OSHA 1926.755(a)(2) specify for the column anchor-rod assembly during erection?
Using 1 refrigeration ton = 12,000 Btu/h, how many tons of cooling correspond to a scheduled capacity of 180,000 Btu/h?
On the supplied schematic practice drawing (S-741), what is the sum of the three printed chain dimensions? Use the dimension labels rather than scaling the sloping graphic.
Why are backfill lifts limited in thickness?
The specified resilient flooring and adhesive require slab moisture and pH checks before installation. Testing has not been completed, but the crew wants to meet turnover. What should happen?
The approved backfill procedure limits loose lifts to 8 inches for this soil and compactor. A crew places one 24-inch loose lift. What should be done?
Under 2021 IBC 1507.7.2, what is the minimum roof-deck slope for natural slate shingles?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
Related Study Resources
Previous Question
Six pilaster grout spaces each have a net grout cross-section of 8 in. by 8 in. after all deductions, constant for a height of 10 ft. Ignoring waste, what total grout volume is required, rounded to two decimals?
Next Question
A finish wall area is 1,520 sq ft and paint covers 380 sq ft per gallon. How many gallons are needed for one coat before waste?
