For the owner coordination call, bank excavation is 1215 cy and soil swells 20 percent for hauling. What loose volume is hauled?

Correct Answer

B) 1,458 cy

The calculation gives 1,458 cy for the stated swell volume. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 221.

Answer Options
A
Limit swell volume to 1458 cy
B
1,458 cy
C
Make 1,312 the answer for swell volume
D
Limit swell volume to 1,603

Why This Is the Correct Answer

The calculation gives 1,458 cy for the stated swell volume. Other choices: the distractors come from omitting an adjustment, using the wrong rate, or applying a rounded shortcut for calculation item 221.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.