A mechanical pipe route is shown crossing low in front of a switchboard service area. What coordination response best protects the electrical installation?
Correct Answer
A) Reroute or raise the obstruction so the equipment remains safely accessible for operation and service
Electrical equipment access must be coordinated across trades. A low pipe in the service area can block safe operation and maintenance, so the superintendent should resolve the obstruction before installation. Contract boundaries, warning paint, or awkward maintenance workarounds do not preserve usable access.
Why This Is the Correct Answer
Electrical equipment access must be coordinated across trades. A low pipe in the service area can block safe operation and maintenance, so the superintendent should resolve the obstruction before installation. Contract boundaries, warning paint, or awkward maintenance workarounds do not preserve usable access.
Why the Other Options Are Wrong
Option B: Allow the pipe because it is not part of the electrical contract
A GC cannot ignore an obstruction simply because another trade installed it; cross-trade conflicts are exactly what coordination is for.
Option C: The coordinator should paint the pipe a warning color and leave the route unchanged
Warning paint only marks the pipe; it leaves the physical obstruction in the worker's service area.
Option D: Ask electricians to use a shorter ladder during maintenance
Making electricians work around a low obstruction is a maintenance workaround, not a coordinated construction solution.
Memory Technique
Picture a gate on the jobsite; electrical equipment overhead obstructions is solved by the action that leads to Reroute or raise the obstruction so the equipment remains safely accessible for operation and service.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use by topic index - switchboards / access coordination to confirm that Electrical equipment access must be coordinated across trades.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
