A straight ladder is set for construction access. Which setup matches the usual 4-to-1 ladder angle rule?
Correct Answer
A) Base 1 ft out for each 4 ft of vertical rise
The 4-to-1 rule places the ladder base about 1 ft out for each 4 ft of height. Tying off does not eliminate the angle requirement.
Why This Is the Correct Answer
The 4-to-1 rule places the ladder base about 1 ft out for each 4 ft of height. Tying off does not eliminate the angle requirement.
Why the Other Options Are Wrong
Option B: Base 4 ft out for each 1 ft of rise
Choice B (Base 4 ft out for each 1 ft of rise) is rejected because Base 4 ft out for each 1 ft of rise is not the OSHA ladder setup, extension, or access dimension cited here.
Option C: Make base flush against the wall the answer for this requirement
In general project requirements, Base flush against the wall is the wrong selection for OSHA ladder pitch: it points to Base flush against the wall, but.
Option D: Any angle if the ladder is tied off
The trap in D is Any angle if the ladder is tied off. That selection is wrong because it answers the OSHA ladder pitch prompt with the wrong practical move.
Memory Technique
Make OSHA ladder pitch a tabbed card: cite the exact condition, then choose Base 1 ft out for each 4 ft of vertical rise.
Reference Hint
Open 29 CFR Part 1926 (OSHA Construction Standards), 1926-2023 / PSI OSHA Excerpts 2025; use 29 CFR 1926 Subpart X - Β§1926.1053 to confirm that The 4-to-1 rule places the ladder base about 1 ft out for each 4 ft of height.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Below-grade reinforced masonry is specified with Type S mortar. Which 28-day compressive strength value should be recognized for Type S under the common ASTM property table?
Next Question
A mechanical pipe route is shown crossing low in front of a switchboard service area. What coordination response best protects the electrical installation?
