On a multistory steel frame, unfinished bolting or welding is progressing above the uppermost permanently secured floor. What OSHA limit applies?
Correct Answer
B) Four floors or 48 ft, whichever is less
OSHA 1926.754(b)(2) limits unfinished bolting or welding to not more than four floors or 48 ft, whichever is less, above the foundation or uppermost permanently secured floor, except where structural integrity is maintained by design. Other choices confuse different erection-progress limits.
Why This Is the Correct Answer
OSHA 1926.754(b)(2) limits unfinished bolting or welding to not more than four floors or 48 ft, whichever is less, above the foundation or uppermost permanently secured floor, except where structural integrity is maintained by design. Other choices confuse different erection-progress limits.
Why the Other Options Are Wrong
Option A: Two floors or 30 ft, whichever is less
The trap in A is Two floors or 30 ft, whichever is less. That selection is wrong because Two floors or 30 ft, whichever is less is a different published number than the cited Unfinished bolting or welding value; 29 CFR 1926.754(b)(2) supports Four floors or 48 ft, whichever is less; Unfinished bolting or welding is limited.
Option C: Eight floors with no height cap
Choice C (Eight floors with no height cap) is rejected because it points to Eight floors with no height cap, but.
Option D: Six floors or 60 ft, whichever is greater
In metals work, Six floors or 60 ft, whichever is greater is the wrong selection for Unfinished bolting or welding: Six floors or 60 ft, whichever is greater is a different published number than the cited Unfinished bolting or welding value; 29 CFR 1926.754(b)(2) supports Four floors or 48 ft, whichever is less.
Memory Technique
Treat unfinished bolting or welding like a labeled shelf; only the matching condition belongs with Four floors or 48 ft, whichever is less.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.754(b)(2) to confirm that OSHA 1926.754(b)(2) limits unfinished bolting or welding to not more than four floors or 48 ft, whichever is less, above the foundation or uppermost permanently secured floor, except where structural integrity is main...
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
