NASCLAProcurement and Contracting Requirementsmedium

A CCD directs immediate work while price is unresolved. What field record is most important?

Correct Answer

C) Daily force-account records of labor, equipment, material, and production.

When price is unresolved, contemporaneous cost records support later adjustment.

Answer Options
A
The contractor should use the original estimate summary without daily quantity support
B
The contractor should use a monthly schedule update without labor or material detail
C
Daily force-account records of labor, equipment, material, and production.
D
The contractor should use a closeout checklist prepared after the directed work is complete

Why This Is the Correct Answer

When price is unresolved, contemporaneous cost records support later adjustment.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.