A CCD directs immediate work while price is unresolved. What field record is most important?

Correct Answer

C) Daily force-account records of labor, equipment, material, and production.

When price is unresolved, contemporaneous cost records support later adjustment.

Answer Options
A
The contractor should use the original estimate summary without daily quantity support
B
The contractor should use a monthly schedule update without labor or material detail
C
Daily force-account records of labor, equipment, material, and production.
D
The contractor should use a closeout checklist prepared after the directed work is complete

Why This Is the Correct Answer

When price is unresolved, contemporaneous cost records support later adjustment.

Why the Other Options Are Wrong

Option A: The contractor should use the original estimate summary without daily quantity support

Choice A gives Only the bid opening roster. Its specific error: it tries to bypass the Change directive cost tracking checkpoint.

Option B: The contractor should use a monthly schedule update without labor or material detail

Choice B (Only the project logo) is rejected because it leaves the work at an informal or incomplete stage, while Change directive cost tracking requires Daily force-account records of labor, equipment, material, and production.

Option D: The contractor should use a closeout checklist prepared after the directed work is complete

The trap in D is Only the final cleaning checklist. That selection is wrong because the action skips the timing, documentation, or field-control step needed for Change directive cost tracking.

Memory Technique

Picture a checkpoint on the jobsite; change directive cost tracking is solved by the action that leads to Daily force-account records of labor, equipment, material, and production.

Reference Hint

Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "CCD cost records" to confirm that When price is unresolved, contemporaneous cost records support later adjustment.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.