Bank excavation is 1,035 cubic yards and soil swells 20 percent for hauling. What loose volume is hauled?

Correct Answer

B) 1,242 cy

Loose volume is 1,035 x 1.20 = 1,242 cy.

Answer Options
A
1,104 cy
B
1,242 cy
C
1,200 cy
D
1,328 cy

Why This Is the Correct Answer

Loose volume is 1,035 x 1.20 = 1,242 cy.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your Florida General Contractor exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.