A metal deck crew establishes a controlled decking zone while installing initial deck panels 24 ft above the lower level. What is the maximum CDZ size from any leading edge?
Correct Answer
C) 90 ft wide by 90 ft deep
OSHA 1926.760(c)(3) limits a controlled decking zone to not more than 90 ft wide and 90 ft deep from any leading edge. Other choices either shrink the permitted CDZ unnecessarily or exceed the OSHA maximum.
Why This Is the Correct Answer
OSHA 1926.760(c)(3) limits a controlled decking zone to not more than 90 ft wide and 90 ft deep from any leading edge. Other choices either shrink the permitted CDZ unnecessarily or exceed the OSHA maximum.
Why the Other Options Are Wrong
Option A: 30 ft wide by 30 ft deep
The trap in A is 30 ft wide by 30 ft deep. That selection is wrong because 30 ft wide by 30 ft deep is a different published number than the cited Controlled decking zone value; 29 CFR 1926.760(c)(3) supports 90 ft wide by 90 ft deep; A controlled decking zone is limited to 90 ft wide by 90 ft deep from a leading edge.
Option B: 60 ft wide by 60 ft deep
Choice B gives 60 ft wide by 60 ft deep. Its specific error: 60 ft wide by 60 ft deep is a different published number than the cited Controlled decking zone value; 29 CFR 1926.760(c)(3) supports 90 ft wide by 90 ft deep.
Option D: 150 ft wide by 150 ft deep
In metals work, 150 ft wide by 150 ft deep is the wrong selection for Controlled decking zone: 150 ft wide by 150 ft deep is a different published number than the cited Controlled decking zone value; 29 CFR 1926.760(c)(3) supports 90 ft wide by 90 ft deep.
Memory Technique
Make controlled decking zone a tabbed card: cite the exact condition, then choose 90 ft wide by 90 ft deep.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.760(c)(3) to confirm that OSHA 1926.760(c)(3) limits a controlled decking zone to not more than 90 ft wide and 90 ft deep from any leading edge.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
A work package has earned value of $180,000 and actual cost of $200,000. What is the CPI?
Next Question
A subcontractor's pay application includes major equipment from a sub-tier supplier, but no sub-tier release is provided as required by the subcontract. What payment control is appropriate?