At device trim, several conductors in an outlet box are too short to terminate without pulling tension on the splice. What is the correct quality response?
Correct Answer
B) Provide adequate conductor length by repulling or extending in an approved accessible box before termination
Conductors must be long enough to make safe, inspectable terminations without tension on the splice. The correction is to provide proper length by repulling or by using an approved accessible box; stretching conductors, hiding splices, or removing the grounding path creates unsafe work.
Why This Is the Correct Answer
Conductors must be long enough to make safe, inspectable terminations without tension on the splice. The correction is to provide proper length by repulling or by using an approved accessible box; stretching conductors, hiding splices, or removing the grounding path creates unsafe work.
Why the Other Options Are Wrong
Option A: Stretch the conductors and cover the splice with extra tape, leaving conductor termination quality unverified
Tape cannot fix a splice that is under tension; it conceals a poor termination instead of creating usable conductor length.
Option C: Push the splice behind the finished wall to gain room
A hidden splice behind finished work is not inspectable or maintainable and turns the short-conductor problem into a concealed defect.
Option D: Cut off the device ground first because it carries current only during faults
The equipment grounding conductor is a safety path during faults; cutting it off removes protection rather than solving the length problem.
Memory Technique
Use the phrase "problem, control, result" for conductor termination quality; the result side is Provide adequate conductor length by repulling or extending in an approved accessible box before termination.
Reference Hint
Open Mechanical and Electrical Systems for Construction Managers, 4th Ed., 2024; use by topic index - conductors / boxes / terminations to confirm that Conductors must be long enough to make safe, inspectable terminations without tension on the splice.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass