During initial metal decking, a panel is placed in the controlled decking zone. What is the minimum OSHA safety-attachment count for that panel?
Correct Answer
A) At least two attachments for each metal decking panel
OSHA 1926.760(c)(6) requires safety deck attachments in the CDZ to have at least two attachments for each metal decking panel. Other choices underattach the panel, use the wrong unit, or delay required safety attachment.
Why This Is the Correct Answer
OSHA 1926.760(c)(6) requires safety deck attachments in the CDZ to have at least two attachments for each metal decking panel. Other choices underattach the panel, use the wrong unit, or delay required safety attachment.
Why the Other Options Are Wrong
Option B: Limit safety deck attachments to one attachment at the leading edge only
In metals work, One attachment at the leading edge only is the wrong selection for Safety deck attachments: the option delays or omits the controlling step.
Option C: Use Four attachments by treating the condition as each 100 sq ft
The trap in C is Four attachments for each 100 sq ft. That selection is wrong because Four attachments for each 100 sq ft is a different published number than the cited Safety deck attachments value; 29 CFR 1926.760(c)(6) supports A.
Option D: Treat the condition as requiring no attachment until final deck fastening
Choice D gives No attachment until final deck fastening. Its specific error: it points to No attachment until final deck fastening, but.
Memory Technique
Use a flashing lip memory cue for safety deck attachments: the stem's condition unlocks At least two attachments for each metal decking panel.
Reference Hint
Open 29 CFR Part 1926, Subpart R - Steel Erection; use 29 CFR 1926.760(c)(6) to confirm that OSHA 1926.760(c)(6) requires safety deck attachments in the CDZ to have at least two attachments for each metal decking panel.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass