When is excavation atmosphere testing required before entry?
Correct Answer
A) When oxygen deficiency or a hazardous atmosphere could reasonably be expected
OSHA requires testing before entry when hazardous atmospheres could reasonably be expected in an excavation.
Why This Is the Correct Answer
OSHA requires testing before entry when hazardous atmospheres could reasonably be expected in an excavation.
Why the Other Options Are Wrong
Option B: Base the excavation atmosphere testing response on after backfill
The trap in B is Only after backfill. That selection is wrong because it leaves the work at an informal or incomplete stage, while Excavation atmosphere testing requires When oxygen deficiency or a hazardous atmosphere could reasonably be expected; Excavation atmospheres are tested before entry when hazards could exist.
Option C: Use at lunch breaks as the stated limit in excavation atmosphere testing
Choice C gives Only at lunch breaks. Its specific error: the option delays or omits the controlling step.
Option D: Apply never in construction excavations to the excavation atmosphere testing condition
Choice D (Never in construction excavations) is rejected because it answers the Excavation atmosphere testing prompt with the wrong practical move.
Memory Technique
Link excavation atmosphere testing to its book condition; a different condition means a different answer than When oxygen deficiency or a hazardous atmosphere could reasonably be expected.
Reference Hint
Open 29 CFR Part 1926 (OSHA Construction Standards), 1926-2023 / PSI OSHA Excerpts 2025; use 29 CFR 1926 Subpart P - §1926.651(g) and §1926.651(h) to confirm that OSHA requires testing before entry when hazardous atmospheres could reasonably be expected in an excavation.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions · 70% to pass
Contract Administration
60 questions · 70% to pass
Project Management
60 questions · 70% to pass
