A thermoset single-ply roof membrane is selected for a large low-slope roof. What minimum slope does the IBC list for that roof covering?
Correct Answer
A) 1/4 unit vertical in 12 units horizontal
IBC thermoset single-ply membrane roof provisions use a 1/4:12 minimum slope. Other choices are steeper values associated with other roof-covering types or project preferences.
Why This Is the Correct Answer
IBC thermoset single-ply membrane roof provisions use a 1/4:12 minimum slope. Other choices are steeper values associated with other roof-covering types or project preferences.
Why the Other Options Are Wrong
Option B: 1 unit vertical in 12 units horizontal
Choice B (1 unit vertical in 12 units horizontal) is rejected because 1 unit vertical in 12 units horizontal is an IBC dimensional value for a different stair, door, or egress condition.
Option C: 2 units vertical in 12 units horizontal
In thermal and moisture protection, 2 units vertical in 12 units horizontal is the wrong selection for Thermoset membrane slope: 2 units vertical in 12 units horizontal is an IBC dimensional value for a different stair, door, or egress condition.
Option D: Use 4 units vertical in 12 units horizontal as the thermoset membrane slope threshold
The trap in D is 4 units vertical in 12 units horizontal. That selection is wrong because 4 units vertical in 12 units horizontal is an IBC dimensional value for a different stair, door, or egress condition.
Memory Technique
File thermoset membrane slope under a badge: condition first, number or duty second, answer 1/4 unit vertical in 12 units horizontal.
Reference Hint
Open International Building Code 2021 or 2024; use IBC 2021/2024 Section 1507 thermoset single-ply roofs - slope to confirm that IBC thermoset single-ply membrane roof provisions use a 1/4:12 minimum slope.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass