Why is cost documentation important in a cost-plus contract?
Correct Answer
D) Payment depends on allowable reimbursable costs and fee under the contract.
Cost-plus payment requires records supporting allowable cost and fee.
Why This Is the Correct Answer
Cost-plus payment requires records supporting allowable cost and fee.
Why the Other Options Are Wrong
Option A: The contract price never uses cost records
In procurement and contracting, The contract price never uses cost records. is the wrong selection for Cost-plus audit trail: the choice would not get the project to Payment depends on allowable reimbursable costs and fee under the contract.
Option B: Treat bid alternates as the only cost-plus audit support
The trap in B is Only bid alternates matter. That selection is wrong because it leaves the work at an informal or incomplete stage, while Cost-plus audit trail requires Payment depends on allowable reimbursable costs and fee under the contract.; Cost-plus contracts require documentation of allowable costs.
Option C: Assume the owner has no right to audit cost-plus records
Choice C gives The owner cannot audit costs. Its specific error: it points to The owner cannot audit costs. but.
Memory Technique
Make cost-plus audit trail a purpose cue; if the choice changes the purpose, it cannot be Payment depends on allowable reimbursable costs and fee under the contract.
Reference Hint
Open NASCLA Contractors Guide to Business, Law and Project Management, 14th Ed.; use the index entry or section for "Cost-plus contracts" to confirm that Cost-plus payment requires records supporting allowable cost and fee.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
