A temporary protection task uses 5 workers for 8 hours per day over 4 days. How many labor-hours should be recorded?
Correct Answer
C) 160 labor-hours
Labor-hours are 5 workers x 8 hours/day x 4 days = 160 labor-hours. Other choices omit either worker count, daily hours, or one day of work.
Why This Is the Correct Answer
Labor-hours are 5 workers x 8 hours/day x 4 days = 160 labor-hours. Other choices omit either worker count, daily hours, or one day of work.
Why the Other Options Are Wrong
Option A: 40 labor-hours
labor-hours, choice a: 40 labor-hours equals 5 x 8. That multiplies those two listed numbers.
Option B: 80 labor-hours
labor-hours, choice b: 80 labor-hours backs into 10 when divided by 8; the accepted setup gives 20 on that same base.
Option D: 120 labor-hours
labor-hours, choice c: 120 labor-hours backs into 15 when divided by 8; the accepted setup gives 20 on that same base.
Memory Technique
Store labor-hours with its last math move; nearby answers are usually unfinished versions of 160 labor-hours.
Reference Hint
Open Construction Jobsite Management, 5th Ed.; use the index entry or section for "Labor-hour tracking" to confirm that Labor-hours are 5 workers x 8 hours/day x 4 days = 160 labor-hours.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?