An ironworker crosses an unprotected beam edge 18 ft above the next lower level, and the work is not connector work or initial decking in a controlled decking zone. What fall-protection trigger applies?
Correct Answer
B) More than 15 ft above the lower level
OSHA 1926.760(a)(1) requires fall protection for steel erection employees on walking or working surfaces with an unprotected side or edge more than 15 ft above a lower level, except for the connector and CDZ provisions. Other choices confuse the connector threshold, deck-completion timing, or a story count not used in this rule.
Why This Is the Correct Answer
OSHA 1926.760(a)(1) requires fall protection for steel erection employees on walking or working surfaces with an unprotected side or edge more than 15 ft above a lower level, except for the connector and CDZ provisions. Other choices confuse the connector threshold, deck-completion timing, or a story count not used in this rule.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
The owner wants to occupy an area with minor incomplete work remaining. What document/control is normally used?
Next Question
A crew will work from a slab edge that is 6 ft above the lower roof. Under OSHA construction rules, what protection trigger height applies to the unprotected side or edge?
