A crew will work from a slab edge that is 6 ft above the lower roof. Under OSHA construction rules, what protection trigger height applies to the unprotected side or edge?
Correct Answer
C) 6 ft
OSHA construction fall protection is generally triggered at unprotected sides and edges 6 ft or more above a lower level. Other choices confuse general industry, shipyard, scaffold, or unrelated thresholds.
Why This Is the Correct Answer
OSHA construction fall protection is generally triggered at unprotected sides and edges 6 ft or more above a lower level. Other choices confuse general industry, shipyard, scaffold, or unrelated thresholds.
Why the Other Options Are Wrong
Option A: 4 ft
In general project requirements, 4 ft is the wrong selection for Fall protection trigger height: 4 ft is the wrong OSHA fall-protection number for the item asked.
Option B: 5 ft
The trap in B is 5 ft. That selection is wrong because 5 ft is the wrong OSHA fall-protection number for the item asked.
Option D: 10 ft
Choice D (10 ft) is rejected because 10 ft is the wrong OSHA fall-protection number for the item asked.
Memory Technique
File fall protection trigger height under a inspection mark: condition first, number or duty second, answer 6 ft.
Reference Hint
Open 29 CFR 1926 OSHA Construction Standards; use 29 CFR 1926.501(b)(1) to confirm that OSHA construction fall protection is generally triggered at unprotected sides and edges 6 ft or more above a lower level.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
An ironworker crosses an unprotected beam edge 18 ft above the next lower level, and the work is not connector work or initial decking in a controlled decking zone. What fall-protection trigger applies?
Next Question
The stormwater inspector walks the site and notes this item: how far should a portable ladder extend above an upper landing?
