The owner wants to occupy an area with minor incomplete work remaining. What document/control is normally used?
Correct Answer
D) A substantial completion inspection with punch list and responsibilities.
Substantial completion is documented with remaining work and responsibilities so occupancy and closeout obligations are clear.
Why This Is the Correct Answer
Substantial completion is documented with remaining work and responsibilities so occupancy and closeout obligations are clear.
Why the Other Options Are Wrong
Option A: The owner should use a warranty-cost negotiation before any occupancy review
The trap in A is A bid protest letter. That selection is wrong because the option answers a paperwork, payment, or bonding issue.
Option B: Rely on the superintendent's visual judgment as enough evidence for substantial completion walk
Choice B gives A deleted submittal log. Its specific error: it removes the controlling Substantial completion walk requirement instead of meeting it.
Option C: The owner should use a general safety inspection unrelated to owner occupancy
Choice C (A scaffold tag.) is rejected because it answers the Substantial completion walk prompt with the wrong practical move.
Memory Technique
Remember substantial completion walk by its jobsite consequence: the correct move points to A substantial completion inspection with punch list and responsibilities.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - documentation / submittals / RFIs / closeout to confirm that Substantial completion is documented with remaining work and responsibilities so occupancy and closeout obligations are clear.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Clay brick on a hot, windy day pulls water from the mortar so quickly that joints become stiff before tooling. What field response addresses the masonry problem?
Next Question
An ironworker crosses an unprotected beam edge 18 ft above the next lower level, and the work is not connector work or initial decking in a controlled decking zone. What fall-protection trigger applies?
