The owner wants to occupy an area with minor incomplete work remaining. What document/control is normally used?
Correct Answer
D) A substantial completion inspection with punch list and responsibilities.
Substantial completion is documented with remaining work and responsibilities so occupancy and closeout obligations are clear.
Why This Is the Correct Answer
Substantial completion is documented with remaining work and responsibilities so occupancy and closeout obligations are clear.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
A rooftop unit schedule lists capacity in tons of cooling. In HVAC estimating, one ton of cooling equals what heat-transfer rate?
The bid form asks for a base bid and three alternates. How should the contractor submit alternate pricing?
A specification includes a $40,000 hardware allowance because final selections are pending. How is the allowance treated in the bid?
The earthwork section requires unit prices for unsuitable-soil removal. What is the contract-administration use of those unit prices?
Before the first progress payment, the owner requests a schedule of values. What is its main contract-payment function?
A signed change order is issued for added lobby millwork. Which contract effect should it state?
On the finish plan, locate room R358; then use the finish schedule. What remarks is listed?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
Clay brick on a hot, windy day pulls water from the mortar so quickly that joints become stiff before tooling. What field response addresses the masonry problem?
Next Question
An ironworker crosses an unprotected beam edge 18 ft above the next lower level, and the work is not connector work or initial decking in a controlled decking zone. What fall-protection trigger applies?
