A project logged 2 DART cases and 80,000 labor-hours. What is the DART rate using the 200,000-hour base?

Correct Answer

D) 5.0

DART rate is 2 x 200,000 / 80,000 = 5.0.

Answer Options
A
2.5
B
4.0
C
8.0
D
5.0

Why This Is the Correct Answer

DART rate is 2 x 200,000 / 80,000 = 5.0.

Why the Other Options Are Wrong

Option A: 2.5

dart rate calculation, choice a: 2.5 is produced by 200,000 / 80,000. The error is using that partial/alternate setup.

Option B: 4.0

dart rate calculation, choice c: 4.0 backs into 0.8 when divided by 5.0; the accepted setup gives 1 on that same base.

Option C: 8.0

dart rate calculation, choice d: 8.0 backs into 1.6 when divided by 5.0; the accepted setup gives 1 on that same base.

Memory Technique

Picture a field note labeled DART rate calculation: finish every operation before accepting 5.0.

Reference Hint

Open 29 CFR Part 1926 (OSHA Construction Standards), 1926-2023 / PSI OSHA Excerpts 2025; use OSHA reporting / recordkeeping topic to confirm that DART rate is 2 x 200,000 / 80,000 = 5.0.

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.