A single row of solid blocking is installed between 17 floor joists. Each block is cut 14-1/2 in. long. What total block length is required?
Correct Answer
A) 19.3 ft
Seventeen joists create 16 spaces between joists. Total block length is 16 x 14.5 = 232 in.; 232/12 = 19.3 ft. Other choices count the wrong number of spaces or use a different block length.
Why This Is the Correct Answer
Seventeen joists create 16 spaces between joists. Total block length is 16 x 14.5 = 232 in.; 232/12 = 19.3 ft. Other choices count the wrong number of spaces or use a different block length.
Why the Other Options Are Wrong
Option B: 17.1 ft
blocking length, choice a: 17.1 ft backs into 1.01 when divided by 17; the accepted setup gives 1.14 on that same base.
Option C: 18.1 ft
blocking length, choice b: 18.1 ft backs into 1.29 when divided by 14; the accepted setup gives 1.38 on that same base.
Option D: 20.5 ft
blocking length, choice c: 20.5 ft backs into 41 when divided by 1/2; the accepted setup gives 38.6 on that same base.
Memory Technique
Say the blocking length rule aloud as a chain; the chain ends at 19.3 ft, not an intermediate stop.
Reference Hint
Open Carpentry and Building Construction, 2016; use the index entry or section for "Solid blocking takeoff between floor joists" to confirm that Seventeen joists create 16 spaces between joists.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass