Large-format floor tile is being installed over a slab with visible humps. The tile setter says extra thinset will flatten the floor as work proceeds. What should the superintendent require?
Correct Answer
D) Correct substrate flatness to the tile manufacturer's and project requirements before setting
Large-format tile requires a properly flat substrate; using thinset as a leveling bed can cause poor support and lippage. Other choices hide or create a finish defect.
Why This Is the Correct Answer
Large-format tile requires a properly flat substrate; using thinset as a leveling bed can cause poor support and lippage. Other choices hide or create a finish defect.
Why the Other Options Are Wrong
Option A: Start setting tile and grind high corners later, leaving tile lippage unverified
In finishes, Start setting tile and grind high corners later is the wrong selection for Tile lippage: the choice would not get the project to Correct substrate flatness to the tile manufacturer's and project requirements before setting, which is the Tile lippage result verified by the source.
Option B: The superintendent should use more grout to hide height changes
The trap in B is Use more grout to hide height changes. That selection is wrong because it leaves the work at an informal or incomplete stage, while Tile lippage requires Correct substrate flatness to the tile manufacturer's and project requirements before setting; Tile substrates must meet specified flatness before tile setting begins.
Option C: Accept lippage because large tile is never flat
Choice C gives Accept lippage because large tile is never flat. Its specific error: it points to Accept lippage because large tile is never flat, but.
Memory Technique
Remember tile lippage by its jobsite consequence: the correct move points to Correct substrate flatness to the tile manufacturer's and project requirements before setting.
Reference Hint
Open Principles and Practices of Commercial Construction, 11th Ed., 2024; use the index entry or section for "Tile substrate preparation and flatness" to confirm that Large-format tile requires a properly flat substrate; using thinset as a leveling bed can cause poor support and lippage.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass