Rigid insulation boards on an exterior wall have open gaps and unsealed joints where the air barrier detail requires continuity. What correction is appropriate?
Correct Answer
C) Correct board fit and seal joints as required by the air/water barrier design
Insulation and air/water barrier details often rely on tight, sealed joints for continuity; open gaps should be corrected according to the design. Other choices ignore air and moisture control or use cosmetic cover-up.
Why This Is the Correct Answer
Insulation and air/water barrier details often rely on tight, sealed joints for continuity; open gaps should be corrected according to the design. Other choices ignore air and moisture control or use cosmetic cover-up.
Why the Other Options Are Wrong
Option A: Leave gaps because insulation only controls temperature
The trap in A is Leave gaps because insulation only controls temperature. That selection is wrong because it tries to bypass the Insulation gaps checkpoint.
Option B: Stuff random scrap material in the joints without sealing
Choice B gives Stuff random scrap material in the joints without sealing. Its specific error: it leaves the work at an informal or incomplete stage, while Insulation gaps requires Correct board fit and seal joints as required by the air/water barrier design.
Option D: Add thicker finish coating to bridge the gaps
In thermal and moisture protection, Add thicker finish coating to bridge the gaps is the wrong selection for Insulation gaps: it answers the Insulation gaps prompt with the wrong practical move.
Memory Technique
Use the phrase "problem, control, result" for insulation gaps; the result side is Correct board fit and seal joints as required by the air/water barrier design.
Reference Hint
Open ANSI/EIMA 99-A-2017, Exterior Insulation and Finish Systems; use the index entry or section for "EIFS insulation board fit and air/water barrier continuity" to confirm that Insulation and air/water barrier details often rely on tight, sealed joints for continuity; open gaps should be corrected according to the design.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
Related Study Resources
Previous Question
As the long-lead tracker is updated, what minimum slope is commonly used for 4 in. gravity drainage pipe?
Next Question
Large-format floor tile is being installed over a slab with visible humps. The tile setter says extra thinset will flatten the floor as work proceeds. What should the superintendent require?
