A CPM activity has early start at the beginning of working day 16 and late start at the beginning of working day 29 on the same calendar. What total float is shown?

Correct Answer

A) 13 days

Using the same schedule calendar, total float = late start − early start =29−16=13 working days. Do not add an inclusive endpoint day. This measures scheduling flexibility, not automatic entitlement to extra payment. Source: https://www.gao.gov/assets/gao-16-89g.pdf

Answer Options
A
13 days
B
12 days
C
14 days
D
16 days

Why This Is the Correct Answer

Using the same schedule calendar, total float = late start − early start =29−16=13 working days. Do not add an inclusive endpoint day. This measures scheduling flexibility, not automatic entitlement to extra payment. Source: https://www.gao.gov/assets/gao-16-89g.pdf

Independent practice; verify any reference hint against the edition and category permitted for your booking. Official exam and reference-list sources →

Was this explanation helpful?

More NASCLA Questions

People Also Study

Related Study Resources

Practice More Contractor Exam Questions

Access all practice questions with progress tracking and adaptive difficulty to pass your contractor license exam.

Start Practicing

Disclaimer: EstatePass is an independent exam preparation platform and is not affiliated with, endorsed by, or connected to any state contractor licensing board, the Construction Industry Licensing Board (CILB), the Department of Business and Professional Regulation (DBPR), NASCLA, Pearson VUE, PSI, or any government agency. Exam requirements, fees, and regulations change frequently. Always verify current requirements with your state's licensing board before making decisions. Information shown was last verified on the dates indicated and may not reflect the most recent changes.