An alternate in a bid form is best described as:
Correct Answer
B) A separately priced addition or deduction that the owner may accept with the bid
An alternate is separately priced so the owner can accept or reject defined scope changes while comparing bids. Other choices confuse alternates with contingency, internal coding, or closeout documents.
Why This Is the Correct Answer
An alternate is separately priced so the owner can accept or reject defined scope changes while comparing bids. Other choices confuse alternates with contingency, internal coding, or closeout documents.
Why the Other Options Are Wrong
Option A: Classify the condition as a random contingency hidden in the base bid
In procurement and contracting, A random contingency hidden in the base bid is the wrong selection for Alternate: it names a financial document or payment mechanism, not the Alternate action/result stated by A separately priced addition or deduction that the owner may accept with the bid.
Option C: Classify the condition as a subcontractor's private labor code
Choice C gives A subcontractor's private labor code. Its specific error: the choice would not get the project to A separately priced addition or deduction that the owner may accept with the bid, which is the Alternate result verified by the source.
Option D: Classify the condition as a final lien waiver as the only closeout document for alternate
Choice D (A final lien waiver) is rejected because it treats Alternate as optional.
Memory Technique
Attach alternate to a switch: remember the function, then the wording A separately priced addition or deduction that the owner may accept with the bid.
Reference Hint
Open Construction Project Management, 5th Ed. (2022); use the index entry or section for "Alternates" to confirm that An alternate is separately priced so the owner can accept or reject defined scope changes while comparing bids.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass
