Out of 500 inspected units, 35 require rework. What is the rework percentage?
Correct Answer
D) 7%
Rework percentage is 35 / 500 = 0.07 = 7%.
Why This Is the Correct Answer
Rework percentage is 35 / 500 = 0.07 = 7%.
Why the Other Options Are Wrong
Option A: 5%
rework percentage, choice a: 5% omits a required add-on/subtraction; the numeric gap is 2.
Option B: 12%
rework percentage, choice c: 12% backs into 0.34 when divided by 35; the accepted setup gives 0.2 on that same base.
Option C: 14%
rework percentage, choice d: 14% backs into 0.4 when divided by 35; the accepted setup gives 0.2 on that same base.
Memory Technique
Picture a badge labeled rework percentage: finish every operation before accepting 7%.
Reference Hint
Open Construction Jobsite Management, 5th Ed. (2024); use by topic index - quality control / nonconformance / corrective action to confirm that Rework percentage is 35 / 500 = 0.07 = 7%.
More NASCLA Questions
Bid instructions require bid security with each sealed bid. Which purpose should the estimator associate with that requirement?
A wood deck surface has 320 sf of coverage. Boards have a 5-1/2 in. actual face width, and the order includes an 8 percent cutting allowance. What linear footage is closest?
Using the dimensions shown for the stabilized construction entrance, what is the plan area?
A reroof area requires 14,720 sf of rigid insulation. Boards are 4 ft by 8 ft, and the order includes 5 percent waste. How many boards are needed?
Two addenda revise the drawings before bid day. What must a responsive bidder normally do with those addenda?
A utility trench is 180 ft long, 3 ft wide, and 7 ft deep with vertical sides inside a trench shield. What excavation volume is required?
A 120 ft long Type C trench is cut with a 4 ft bottom width and a 6 ft depth. If side slopes are 1-1/2 horizontal to 1 vertical, what excavation volume is closest?
A storm pipe run needs 240 ft of bedding, 4 ft wide and 6 in. thick. Including a 10 percent ordering allowance, how many cubic yards of bedding aggregate are needed?
A mass excavation produces 1,180 loose cubic yards of material for off-site disposal. End-dump trucks can haul 18 loose cubic yards per trip. What truck count is required?
An asphalt-shingle roof has a slope of 3:12. Under the IBC low-slope asphalt-shingle provisions, what underlayment arrangement is required?
People Also Study
Business & Financial Management
120 questions Β· 70% to pass
Contract Administration
60 questions Β· 70% to pass
Project Management
60 questions Β· 70% to pass